12 men will take 54 days to complete a building project.

  1. (a)

    Assuming that the men work at the same rate, how long will it take for 9 men to complete the project?

    Answer ___ days

  2. (b)

    How many days can be saved if 6 more men are added to the team?

    Answer ___ days

Work through it with AI →

It won't just hand you the answer — it asks where you're stuck.How the checker works

Worked solution

21(a)

1. Find the total work in man-days and divide by the new number of men.

For the same building project,
men×days=constant.\text{men} \times \text{days} = \text{constant}.
12×54=9×d12 \times 54 = 9 \times d
d=12×549=72d = \frac{12 \times 54}{9} = 72

Answer

7272 days

21(b)

1. Find the time taken when 6 more men are added to the original team.

Number of men =12+6=18=12+6=18

Total work =12×54=648=12\times54=648 man-days

Time taken by 1818 men =64818=36=\dfrac{648}{18}=36 days

2. Find the number of days saved compared with the original time.

Days saved =54−36=18=54-36=18 days

Answer

1818 days

AI analysis — may contain mistakes.

Worked this one out on paper? Snap your steps and Gigle's AI math checker will circle the step where it went wrong.

More questions on this topic

  1. 1Mrs Ang runs a small tuition centre for secondary school students. The tables provide information on the cost of running…
  2. 2On 1st January 2018, Mrs Yeo invests $15000 in an account which pays at a rate of compound interest of RR% per year. O…
  3. 3A cuboid has a volume of 250 cm^3, correct to the nearest cubic centimetre. The height of the cuboid is 8.4 cm, correct…
  4. 4Hamid borrowed a sum of money for 3 years at an interest rate of 3.5% per annum simple interest to pay for his car. If t…
  5. 5The diagram shows the positions of a harbour, H, a lighthouse, L, and two buoys P and Q. HPQ is a straight line. The bea…