Given that 4500 workers, each working 8 hours a day, will complete the Thomson Line in 1800 days.
If 4800 workers work on the project with each worker working for 10 hours a day, find the number of days it would take to complete the project.
Answer ... days
It won't just hand you the answer — it asks where you're stuck.How the checker works
Worked solution
1(a)
1. Clear the fractions by cross-multiplication.
2. Rearrange to find the ratio $\frac{a}{b}$.
1(b)(i)
1. Complete the square for the quadratic expression.
1(b)(ii)
1. Substitute the completed-square form into the equation.
From part (b)(i),
So
2. Solve the equation by isolating the squared term and taking square roots.
3. Evaluate both roots and round to two decimal places.
Therefore, to two decimal places,
or
1(c)
1. Find the total amount of work in worker-hours.
Total work worker-hours.
2. Divide the same total work by the new daily work rate to find the number of days.
Let the required number of days be .
days
AI analysis — may contain mistakes.
Worked this one out on paper? Snap your steps and Gigle's AI math checker will circle the step where it went wrong.
More questions on this topic
- 1Hamid borrowed a sum of money for 3 years at an interest rate of 3.5% per annum simple interest to pay for his car. If t…
- 2By completing the square or otherwise, express in terms of given that . Answer x = ___ or ___…
- 3It is given that Obtain an expression for in the form…
- 4In the diagram, AB is a tangent to the circle with centre O, ∠CAB = 58° and CDE is a straight line. Find, stating your r…
- 5已知方程,用含的代数式表示为:___.