A factory prints posters for corporate events. The prices of printing posters of different sizes are listed below. The factory has the following guidelines for operating the printers.

  1. (a)

    Given that 1 inch = 2.54 cm, find the area of a bulletin poster in m^2.

    Answer ... m^2

  2. (b)

    Mr Tan wants to print 1200 bulletin posters for an event. Calculate how much does it cost.

    Answer $ ...

  3. (c)

    The factory uses 2 printers to print Mr Tan's order for an entire day. The older printer takes 15 seconds more to print one bulletin poster compared to the newer printer and the rates of printing of the 2 printers are constant throughout the day.

    An operator of the printers claims that the older printer needs servicing. Do you agree? Justify your answers with clear working.

    Answer

Work through it with AI →

It won't just hand you the answer — it asks where you're stuck.How the checker works

Worked solution

9(a)

1. Convert the poster dimensions to centimetres and find the area in square centimetres.

Bulletin poster size: 11×1711 \times 17 inches.

Since 11 inch =2.54=2.54 cm,
11 inches=11×2.54=27.94 cm11\text{ inches}=11\times2.54=27.94\text{ cm}
17 inches=17×2.54=43.18 cm17\text{ inches}=17\times2.54=43.18\text{ cm}
Area
=27.94×43.18=120.6448 cm2=27.94\times43.18=120.6448\text{ cm}^2

2. Convert the area from square centimetres to square metres.

Since 1 m=100 cm1\text{ m}=100\text{ cm},
1 m2=10000 cm21\text{ m}^2=10000\text{ cm}^2
120.6448 cm2=120.644810000=0.01206448 m2120.6448\text{ cm}^2=\frac{120.6448}{10000}=0.01206448\text{ m}^2

Answer

0.01206448 m20.01206448\text{ m}^2

9(b)

1. Identify the price per bulletin poster.

From the table, the price of one bulletin poster is $2.00.

2. Multiply the unit price by the number of bulletin posters.

Cost of 12001200 bulletin posters

1200×2.00=24001200 \times 2.00 = 2400

Answer

$2400

9(c)

1. Find the actual printing time available in one day.

The printer operates from 9.00 am to 4.00 pm, which is 77 hours.

It must cool for 3030 minutes after every 22 hours of printing.

A possible schedule is:

9.009.00 am to 11.0011.00 am: print 22 h

11.0011.00 am to 11.3011.30 am: cool 0.50.5 h

11.3011.30 am to 1.301.30 pm: print 22 h

1.301.30 pm to 2.002.00 pm: cool 0.50.5 h

2.002.00 pm to 4.004.00 pm: print 22 h

So the total printing time is

2+2+2=6 h2+2+2=6\text{ h}

6 h=6×60×60=21600 s6\text{ h}=6\times 60\times 60=21600\text{ s}

2. Form an equation for the number of posters printed by both printers.

Let the newer printer take xx seconds to print one bulletin poster.

Then the older printer takes x+15x+15 seconds to print one bulletin poster.

In 2160021600 seconds,

number printed by newer printer =21600x=\dfrac{21600}{x},

number printed by older printer =21600x+15=\dfrac{21600}{x+15}.

Together, they print 12001200 posters, so

21600x+21600x+15=1200\frac{21600}{x}+\frac{21600}{x+15}=1200

3. Solve the equation to find the time taken by each printer per poster.

Divide the equation by 12001200:

18x+18x+15=1\frac{18}{x}+\frac{18}{x+15}=1

Multiply throughout by x(x+15)x(x+15):

18(x+15)+18x=x(x+15)18(x+15)+18x=x(x+15)

18x+270+18x=x2+15x18x+270+18x=x^2+15x

36x+270=x2+15x36x+270=x^2+15x

x2−21x−270=0x^2-21x-270=0

(x−30)(x+9)=0\left(x-30\right)\left(x+9\right)=0

Since time cannot be negative,

x=30x=30

So the newer printer takes 3030 seconds per poster, and the older printer takes

30+15=45 seconds per poster.30+15=45\text{ seconds per poster}.

4. Find the total area printed by the older printer in one day.

Number of posters printed by the older printer in one day:

2160045=480\frac{21600}{45}=480

From part (a), area of one bulletin poster is

0.01206448 m20.01206448\text{ m}^2

Total area printed by the older printer:

480×0.01206448=5.791 m2 approximately480\times 0.01206448=5.791\,\text{m}^2\text{ approximately}

5. Compare the older printer's daily printing area with the servicing guideline and conclude.

The printer needs servicing if its rate of printing has slowed down to less than 60 m260\text{ m}^2 a day.

For the older printer,

5.791 m2<60 m25.791\text{ m}^2<60\text{ m}^2

Therefore, the older printer needs servicing.

Answer

Yes, I agree. The older printer prints about 5.79 m25.79\text{ m}^2 in a day, which is less than 60 m260\text{ m}^2, so it needs servicing.

AI analysis — may contain mistakes.

Worked this one out on paper? Snap your steps and Gigle's AI math checker will circle the step where it went wrong.

More questions on this topic

  1. 1A piece of wood which was 50 cm long, was in the shape of a uniform cylinder. A prism is cut out from the wood such that…
  2. 2The picture shows a model terracotta warrior. The model has height of 15 cm and weighs 20 grammes. A similar terracotta…
  3. 3An industrial mixer is made up of an open cylinder connected to a cone. The height of the cylinder and the cone is 1.2 m…
  4. 4The volume of an Olympic size swimming pool is 660 000 gallons. 1 gallon is approximately 3790 cm^3. Convert 660 000 gal…
  5. 5A lake has an actual area of 2.56 km^2. It is represented by an area of 4 cm^2 on a map. Find the scale of the map in th…